What date supports the financing model?
Use the date when the relevant part of the site can support the intended racks under the design conditions. A utility feasibility discussion, a service agreement, energized electrical infrastructure, facility commissioning, and customer acceptance each describe a different milestone. Record the megawatts available at each phase and the conditions attached to that capacity. Metered facility load includes more than IT equipment, so confirm the power available to the racks with the facility engineer.
Dominion Energy's Virginia data center process illustrates staged service. It begins with inputs including a site plan, load letter, and ramp schedule. The utility describes an initial power solution for some projects before final service infrastructure is complete. A lender still needs the service terms and schedule for the specific project. Dominion Energy, Virginia data center requests
What documents support each stage of readiness?
| Milestone | Evidence | Financing implication |
|---|---|---|
| Service plan | Utility correspondence, capacity schedule, required upgrades, and responsibility for their cost | Estimate scope and model dependencies still outside the borrower's control |
| Service committed for a phase | Executed agreements and the conditions, dates, and capacity they specify | Match hardware orders and draw requests to the covered phase |
| Facility ready to test | Energization and commissioning records for power, cooling, and the applicable redundancy configuration | Confirm the site can sustain the required rack load |
| Customer can use the cluster | Hardware and network sign-off and acceptance evidence under the customer order | Check the actual start of contracted revenue |
Read the customer contract and the electrical and facility records together. Account for the time between utility service and a usable cluster, including commissioning, installation, and retests. Determine whether the financing and customer contracts measure the same event when they refer to delivery.
How does a delay affect funding and cash flow?
Illustrative. A project plans 12 MW of usable IT capacity in two phases. The facility engineer confirms that the first phase supports 4 MW. The first customer acceptance milestone covers racks that fit in that phase. Other racks depend on a second phase whose switchgear delivery moves by eight weeks. A model that starts billing across all 12 MW at first energization brings revenue forward before the site can support the second phase. Compare financing the first phase by itself with financing equipment for both phases and carrying the second phase's costs before it earns revenue.
Before the next equipment commitment, ask the utility and construction leads to confirm remaining conditions, then have the finance team revise the draw and revenue schedule. Identify which supplier deadlines the project can move and what liquidity it needs if those deadlines stay fixed.
Can temporary service support a permanent buildout?
Evaluate temporary service on its own documented terms. Check how much load it supports, when it ends, how service transitions to the permanent arrangement, and whether the customer can accept that configuration. If one phase relies on an upgrade, include a separate delay case for that upgrade.
See GPU financing draw conditions for the funding side and GPU cluster acceptance testing for the evidence that establishes usable capacity.
Source
- Dominion Energy, Virginia data center service request and connection process, reviewed November 22, 2026.
Last updated on
Have a financing question?
Bring the capacity, delivery window, and financing question. Start with the cash required to deliver and the conditions that start customer payments.
Email hello@computeneutral.com or book a call with our team.
Discuss a financing