Do the offers fund the same costs?
Read the permitted use of proceeds and the definition of eligible cost. An offer covering GPU servers can leave freight, networking, installation, and prepaid capacity to the borrower. Ask which invoices qualify, when they must be submitted, and when they can be reimbursed. Compare usable proceeds on the dates you owe the supplier.
Illustrative. An order has $800,000 of servers and $200,000 of other costs. Offer A advances 75% against eligible servers, or $600,000. Offer B advances 65% of the full $1 million cost, or $650,000. Assuming equal timing and no fees, Offer A leaves $400,000 for the buyer to cover and Offer B leaves $350,000. These percentages are assumptions for the example.
When is each draw available?
Map the signing deposit, equipment invoice, delivery, acceptance, and any reimbursement date. Record each financing condition, the evidence needed, and who controls it. Two facilities with the same commitment can produce different peak cash needs if one first funds at delivery and the other reimburses after acceptance.
What does the borrower give up for that funding?
| Compare | Put both offers on the same basis |
|---|---|
| Cash at signing | Upfront fees, sponsor cash, and any reserve funded at closing |
| Cash during service | Interest, principal, recurring fees, reserves, and the balance due at maturity |
| Control | Collateral, restrictions on refinancing or asset replacement, and any guarantees |
| Exit | Prepayment cost, early termination terms, and steps to release existing security |
| Downside | Cost and minimum cash balance if delivery slips or an anchor customer pays late |
CoreWeave’s quarterly filing illustrates several distinct financing terms in one facility, including the draw window, equipment cost constraint, collateral, and required repayments. The disclosed terms are evidence about that facility. A borrower should get the same fields from each offer it is comparing.
What makes the comparison usable?
Make a single dated cash forecast with one column per offer. Show committed funds separately from indications, and identify the largest unfunded point in each plan. Reconcile the forecast with the compute contract signing guide, especially the dates that determine when cash is due and when service begins.
Source
- CoreWeave, third-quarter 2026 Form 10-Q, Note 10, Debt, reviewed November 22, 2026.
Last updated on