# How to size financing for a GPU capacity deposit

Size a deposit financing against the cash actually due before service and the amount available by each invoice deadline. Model borrower cash, fees, and a delivery delay before choosing the requested amount.

## What counts toward the upfront cash need?

Start with the provider’s dated invoices. Record which amounts are deposits, which become service credits, which become earned at a milestone, and which are refundable under the contract. Add financing fees payable by closing, agreed reserves, and any other amounts the borrower must pay from its own cash before service starts.

![A clock face with fine minute ticks beside an hourglass, the sand settled in its lower bulb.](https://computeneutral.com/assets/editorial/how-to-size-a-compute-commitment-plate.svg)

Then subtract confirmed funding available by each deadline and the borrower cash allocated to that payment. A commitment that can only draw at acceptance cannot cover an earlier deposit unless another agreed source bridges the gap.

## How does the calculation work?

Illustrative. A provider invoice requires $300,000 at signing. The borrower commits $100,000 and a facility makes $180,000 available against that invoice. The borrower still needs $20,000 at signing. If the upfront financing fee is $6,000 and the borrower pays it then, the funding gap rises to $26,000.

| Input | Cash effect at signing |
| --- | --- |
| Provider deposit due | $300,000 |
| Financing fee due | $6,000 |
| Borrower cash allocated | ($100,000) |
| Facility cash drawable | ($180,000) |
| Unfunded amount | $26,000 |

CoreWeave’s annual report describes prepayments under some committed contracts and how they are applied. Use the signed order to establish how your own deposit reduces future invoices. The cash transferred and the credit earned can occur at different times.

## What changes if the service start moves?

Move the first service credit and first customer collection by the length of the delay. Keep each financing payment on its contractual date unless the facility expressly moves it. Then assess the largest cash deficit before service and compare the result with available liquidity. Also record when a refund becomes due and the expected time to receive it if the order terminates.

## What goes into the financing request?

Bring the order, dated invoice schedule, eligible uses, borrower contribution, fee schedule, and the evidence for each draw. Show the earliest date funds are needed and the amount still uncovered in the delayed case. For ways to structure the payment itself, see [how to fund an upfront payment to a GPU provider](https://computeneutral.com/guides/prepayment-vs-pay-over-time).

## Source

- [CoreWeave, 2025 Form 10-K, committed contracts and revenue recognition](https://www.sec.gov/Archives/edgar/data/1769628/000176962826000104/crwv-20251231.htm), reviewed November 22, 2026.

Last updated on November 22, 2026

## Have a financing question?

Bring your workload and planned start date. Start with when you need usable capacity, when cash is due, and what the agreement protects.